Scope of work: Remove
a ferry dock destroyed in Hurricane Isabel, then replace it
with a public fishing pier.
The 500-foot long pier is 12-foot wide with a 200-foot by
10-foot "T" at the end. Supported by 300 timber piles 20 to
35-foot long, the pier is constructed of 3-inch framing and
2-inch decking. A full length timber hand rail, benches and
pedestrian lighting completed the pier design. The project
also included 265 LF of timber bulkhead, an asphalt parking
lot, and a canoe launch.
|